How do I assign resources from a resource pool to the sharer project - Microsoft Community


i have master project file have linked 10 or sub-projects has been running nicely months track schemes , jobs (without need resources).

now want assign resources (work, not material or cost) jobs within master/sub-project set-up.

i have created brand new project file (resource pool), input of work resources, saved same location master project , shared pool master way of resoucrce pool > share resources.

all good, or thought.........

now, though, can't work out how assign resources resource pool jobs held within master/sub set up?!?  do need open each sub-project file individually , share resource pool each of 10 sub's , assign within or there way assign resources having master project , resource pool open?

anyone able help, i'm sure i'm being bit stupid!

by way i'm using ms project 2010.

thanks.

bully of smeg --

you need connect each subproject shared resource pool file.  allow assign resources in each of subprojects.  hope helps.



Office / Project / Windows other / Office 2010



Comments

Popular posts from this blog

message deleted by transport agent, event: LED=550 4.3.2 - Microsoft Community

Microsoft Office Exchange Error message - Microsoft Community

Outlook Rules not Running Automatically - Microsoft Community