hi,
i looking way have resource usage view default the collapsed outline, lists resources instead of resources , of subtasks.
can done?
pierre
pete213 --
in microsoft project, definition of view follows:
view = table + filter + group + screen
notice outline level not part of definition of view. because of this, cannot specify resource usage view show resources, task assignments collapsed. in each individual project, however, can use outline button ribbon collapse of assignments . apply resource usage view , click select button select every resource , task assignment. in data section of view ribbon, click outline > hide subtasks collapse each resource's task assignments see resources.
hope helps.
Office / Project / Other/unknown / Office 2010
Comments
Post a Comment