hello everybody, 

i know if possible split summary task in project.

thanks in advance

irene,

simple answer "no", @ least if referring split task function in project.

please note summary task not task @ despite name, rather summary of tasks under it. start of summary line defined start of earliest subtask , finish of summary line defined finish of latest subtask.

you can "split" summary breaking subtasks under 2 separate summary groups. "split" summary task.

hope helps.

john