Task Type: Fixed Work Question - Microsoft Community
Office / Project / Windows 10 / Office 2016
hi, majority of tasks need work fixed customer paying hour. e.g task might take week in total complete might want schedule 3 hrs of work first day, 2hrs second day, 5hrs third day etc etc.
is best set task type fixed work, , set duration 1 week go resource usage view , manually input hours each day?
any advice gratefully rec'd. thanks
anita,
why not enter work , duration , let project linearly spread work on duration. doing manual adjustment you'll have "sneak up" on work value enter work each day. there value in doing that?
john
Office / Project / Windows 10 / Office 2016
Comments
Post a Comment