why ms project allocate tasks saturdays , sundays though non working days?
i using standard calendar project , resources weekends showing non working yet tasks still allocated saturdays.
***post moved moderator appropriate forum category.***
steve,
based on additional information provided latest screen shot, i'd exe resource has custom resource calendar includes working weekends , perhaps non-default work hours. example, take @ task 44. starts on 3/4/17 , finishes on 11/4/17 10 day duration. given 8 hour day , standard calendar, task finish on 14/4/17, not 11/4/17.
john