i'm using ms project pro 2013 on windows 7. i have several projects sharing same resource pool, , i'm entering tasks in 1 of projects, shows 1 of resources over-allocated.
so brought resource usage sheet, , sure enough, says i've assigned 9h of work resource in 8h day. however, scan through list of tasks resource assigned find offending task put him on limit, can't tell project task belongs. is there way show projects tasks belong in view?
thanks.
tim,
sure, when viewing resource pool, add project field resource usage view.
hope helps.
john