Determining to Which Projects a Shared Resource is Assigned - Microsoft Community


hi,

i'm using ms project pro 2013 on windows 7.  i have several projects sharing same resource pool, , i'm entering tasks in 1 of projects, shows 1 of resources over-allocated.

so brought resource usage sheet, , sure enough, says i've assigned 9h of work resource in 8h day.  however, scan through list of tasks resource assigned find offending task put him on limit, can't tell project task belongs.  is there way show projects tasks belong in view?

thanks.

tim,

sure, when viewing resource pool, add project field resource usage view.

hope helps.

john



Office / Project / Windows other / Office 2013



Comments

Popular posts from this blog

Outlook Rules not Running Automatically - Microsoft Community

message deleted by transport agent, event: LED=550 4.3.2 - Microsoft Community

Microsoft Office Exchange Error message - Microsoft Community