i looking generate report in msproject 10 (on win7). nothing complex, accomplish following:
-provide me two-week "look-ahead"
-advise me tasks might slip
-advise me on completed tasks
all assumes, of course, schedule up-to-date. there such report whether default or custom has found handy? nothing exotic, useful on regular basis. kind of snapshot , future. , if 2 or 3 reports, please advise that. thanks.
jim,
just reference project 10 implies version 10 project 2002 , assume don't mean that. rather, assume mean project 2010 happens version 14.
as far desired reports there many options. "look ahead" use date range filter. tasks completed, use completed task filter. "tasks might slip" little open ended. if assume schedule "up date", on track (i.e. no slips). constitutes "soon slip"? if can define perhaps 1 of built-in filters can or can create custom filter.
john