MS Project 2013 - issue with sub-project duration, start and finsish - Microsoft Community


i have created master schedule several sub-projects.  first 5 or linked seem have joined master without issue.  last 2 have tried link there ok, though subject line duration, start , finish dates incorrect.  when expand sub-project, correct dates  , duration there in lower lines , tasks - error in top line.  cannot change defaulted auto-schedule, cannot overwrite data.

any ideas?

elliot,

yes, update project 2013. issue fixed december 2016 cumulative update. update, run windows update.

hope helps.

john