split summary task - Microsoft Community


hello everybody, 

i know if possible split summary task in project.

thanks in advance

irene,

simple answer "no", @ least if referring split task function in project.

please note summary task not task @ despite name, rather summary of tasks under it. start of summary line defined start of earliest subtask , finish of summary line defined finish of latest subtask.

you can "split" summary breaking subtasks under 2 separate summary groups. "split" summary task.

hope helps.

john



Office / Project / Other/unknown / Office 2013



Comments

Popular posts from this blog

message deleted by transport agent, event: LED=550 4.3.2 - Microsoft Community

Outlook conversion problem - Microsoft Community

Outlook 2016 - Insert attachment to Meeting Invite You Do Not Own - Microsoft Community